- Pre-qual from Construction Lender or Proof of Funds
Purchase-Build Contract
- Sample Contract
- Docusign
- Earnest Deposit
Great American Title Contact:
Alycia Crook
Great American Title
7055 W Bell Rd. Ste B19
Glendale, AZ 85308
602-393-9846 | [email protected]
NEXTGEN Lot (60 Days)
Day 1-5
- Design Studio appointment set
Day 6-20
- Options selected, & Addendum signed
- Material purchasing begins
Day 21-60
- Bank Appraisal & underwriting
- Close loan - COE
Build on Your Own Lot (120 Days)
Day 1-70
- Field survey, soils report, septic design, engineered grading plan
- Site Addendum signed
Day 70-75
- Design Studio appointment set
Day 76-90
- Options selected, & Addendum signed
- Material purchasing begins
Day 91-120
- Bank appraisal and underwriting
- Close loan - COE
NEXTGEN Lot (Skip)
Engineering & Permitting completed in advance.
Build on Your Own Lot (120 Days)
Submit for Permits
- County: 2 – 3 mo.
- City: 4 – 6 mo.
Meet your building Project Manager
Review the build process & next steps with your Project Manager
Location:
Your new home-site
NEXTGEN Lot (8-9 Months)
- Regular updates from your Project Manager
- 5 draws based on completion stages
Build on Your Own Lot (9-10 Months)
- Regular updates from your Project Manager
- 5 draws based on completion stages
Welcome to your new NEXTGEN Home!
- Certificate of Occupancy - COO