Next Steps

1. Purchase Contract

  • Pre-qual from Construction Lender or Proof of Funds

Purchase-Build Contract

  • Sample Contract
  • Docusign
  • Earnest Deposit

Great American Title Contact:

Alycia Crook

Great American Title
7055 W Bell Rd. Ste B19
Glendale, AZ 85308

602-393-9846   |   alyciac@azgat.com 

2. Pre-Closing

NEXTGEN Lot (60 Days)


Day 1-5

  • Design Studio appointment set

Day 6-20

  • Options selected, & Addendum signed
  • Material purchasing begins

Day 21-60

  • Bank Appraisal & underwriting
  • Close loan - COE

Build on Your Own Lot (120 Days)


Day 1-70

  • Field survey, soils report, septic design, engineered grading plan
  • Site Addendum signed

Day 70-75

  • Design Studio appointment set

Day 76-90

  • Options selected, & Addendum signed
  • Material purchasing begins

Day 91-120

  • Bank appraisal and underwriting
  • Close loan - COE

3. Permitting

NEXTGEN Lot (Skip)


Engineering & Permitting completed in advance.

Build on Your Own Lot (120 Days)


Submit for Permits

  • County: 2 – 3 mo.
  • City: 4 – 8+ mo.

4. Ground Breaking

Meet your building Project Manager
Review the build process & next steps with your Project Manager

Location:
Your new home-site

5. Build

NEXTGEN Lot (8-9 Months)


  • Regular updates from your Project Manager
  • 5 draws based on completion stages

Build on Your Own Lot (9-10 Months)


  • Regular updates from your Project Manager
  • 5 draws based on completion stages

6. Move In

Welcome to your new NEXTGEN Home!

  • Certificate of Occupancy - COO

Construction Lenders

AZFCU

Thad Flores,
NMLS# 989577

(480) 275-0032
thad.flores@azfcu.org

 

usbank

Steve Asiala
NMLS# 503417

(480) 208-1579
stephen.asiala@usbank.com